Building Owner Party Wall Guidance

1. Section 1 Notice – Line of Junction Notice

Required when:

  • You plan to build a new wall up to or along the boundary line.
  • You propose to build a wall astride the boundary (a party fence wall), subject to neighbour’s consent.

📌 Notice period: At least 1 month before works begin.
⚠️ If the new wall’s foundations are deeper than your neighbour’s, a Section 6 Notice may also be required.


2. Section 3 Notice – Party Structure Notice

Required when you intend to carry out works directly affecting an existing party wall or structure. Examples include:

  • Cutting into a wall to insert beams, flashings, or a damp proof course.
  • Removing chimney breasts or other projections.
  • Raising, rebuilding, repairing, or underpinning a party wall.
  • Enclosing upon a wall at the boundary and turning it into a party wall.

📌 Notice period: At least 2 months before works begin.


3. Section 6 Notice – Notice of Adjacent Excavation

Required when excavating near your neighbour’s property. This applies if you are:

  • Excavating within 3 metres of their foundations to a lower depth, or
  • Excavating within 6 metres, where the works will go below a line drawn at 45° from the bottom of their foundations.

📌 Notice period: At least 1 month before works begin.
📎 Plans and cross-sections of the proposed works must be included with the notice.


Need Expert Help?

Serving a Party Wall Notice correctly is the first step in avoiding costly disputes and project delays.

📩 For free advice or to have your notices prepared by qualified surveyors at the UK’s lowest cost, contact us today at team@simplesurvey.co.uk.